NEW QUESTION 1
Which of the following activities typically would be an appropriate application of the ISO 31000 Risk Management Principles and Guidelines?

  • A. Calculating a risk index for each facility
  • B. Establishing external risk communications processes
  • C. Projecting the ability of a facility to recover from an event
  • D. Preparing for risk management accreditation

Answer: B

NEW QUESTION 2
Which of the following factors is most important to consider when deciding on offshore outsourcing of manufacturing to a supplier?

  • A. Size of the supplier organization
  • B. Total cost of ownership
  • C. Supplier performance history
  • D. Supplier certification

Answer: B

NEW QUESTION 3
Which of the following actions is most likely to improve the cash-to-cash cycle time?

  • A. Find suppliers with lower total cost of ownership (TCO)
  • B. Implement vendor-managed inventory (VMI) with key suppliers
  • C. Implement vendor-managed inventory (VMI) with key customers
  • D. Establish targeted promotions for the most profitable market segments

Answer: B

NEW QUESTION 4
Which of the following activities occurs as part of the sales and operations planning process?

  • A. Time fences are matched to master production schedule horizons.
  • B. The next quarter's forecasts are presented by sales staff to finance and operations personnel at the final meeting.
  • C. Strategic plans are adjusted based on changing operating situations.
  • D. Plans are converted to financial projections and capacity requirements.

Answer: D

NEW QUESTION 5
An operations manager wants to measure variability in the delivery time of insurance policies to clients. Which of the following quality tools most appropriately would show the level of variability?

  • A. Pareto chart
  • B. Histogram
  • C. Scatterplot
  • D. Check sheet

Answer: B

NEW QUESTION 6
Which of the following situations is a consequence of global operations?

  • A. Decreased logistic cost
  • B. Increased logistic complexity
  • C. Reduced product variety
  • D. Longer lead times

Answer: B

NEW QUESTION 7
Value stream mapping provides the most benefit when:

  • A. analyzing customer requirements.
  • B. identifying nonvalue-added activities.
  • C. planning kaizen events.
  • D. implementing an information technology strategy.

Answer: B

NEW QUESTION 8
A large manufacturer wanting to be more competitive in the global market place decided to outsource its transportation and return processing to other companies on a contractual basis. The companies providing the services would be referred to as:

  • A. fourth party logistics providers.
  • B. third party logistics providers.
  • C. retail services providers.
  • D. distribution services providers.

Answer: B

NEW QUESTION 9
A company that sells engineered-to-order products is planning implementation of a supplier relationship management system (SRM) for direct materials. Which of the following factors is most likely to make the implementation difficult?

  • A. Complexity of the purchasing process
  • B. Cost of the application software upgrades
  • C. Management of variable lead times
  • D. Resistance of material suppliers

Answer: A

NEW QUESTION 10
Which of the following objectives is the primary driver in the design and implementation of lean process management?

  • A. Reducing the level of inventory
  • B. Decreasing the cash-to-cash cycle
  • C. Integrating processes between departments
  • D. Satisfying customer requirements

Answer: D

NEW QUESTION 11
Short order cycles to facilitate rapid replenishment will result in:

  • A. minimal in-process inventory.
  • B. fewer inventory moves.
  • C. improved communications to customers.
  • D. increased supplier collaboration.

Answer: A

NEW QUESTION 12
In the Supply Chain Operations Reference-model (SCORĀ®), the cash-to-cash cycle time for a manufacturing company is the number of days between which two of the following
situations?

  • A. Paying for raw materials and getting paid for the product
  • B. Shipping the product from the warehouse and receiving it at the customer's location
  • C. Paying for raw materials and sending an invoice to the customer
  • D. Billing the customer and getting paid for the product

Answer: A

NEW QUESTION 13
Which of the following statements describes a continuous replenishment strategy in a retail environment?

  • A. Retailers make replenishment decisions.
  • B. Retailers prepare individual orders and share sales data with vendors to improve customer service.
  • C. Vendors use sales data and prepare shipments to maintain the desired level of inventory.
  • D. Vendors take full control of inventory policy.

Answer: C

NEW QUESTION 14
Pull strategy typically would be the most appropriate strategy when customer demand uncertainty is:

  • A. high, and supplier lead time is long.
  • B. high, and supplier lead time is short.
  • C. low, and supplier lead time is long.
  • D. low, and supplier lead time is short.

Answer: B

NEW QUESTION 15
Which of the following actions is most appropriate when implementing a strategy to create customer-affordable value?

  • A. Use a more rapid transportation mode.
  • B. Increase safety stock.
  • C. Extend product warranty.
  • D. Employ lean principles.

Answer: D

NEW QUESTION 16
Which of the following factors is the most important driver of supply chain change?

  • A. Health and safety concerns
  • B. Competitor actions
  • C. Government regulations
  • D. Customer perceptions of value

Answer: D