NEW QUESTION 1
______ can change the priority of items in the ______ backlog at any time.
- A. The Team; Product
- B. The Product Owner(s); Sprint
- C. The Product Owner(s); Product
- D. The Scrum Master; Sprint
Answer: C
NEW QUESTION 2
On a new Scrum Team, the Development Team tell the Scrum Master that they don’t feel the need for retrospectives. Which answer is correct?
- A. Discuss with product owner
- B. Start doing retrospectives
- C. None of above
Answer: C
NEW QUESTION 3
Which of the following is a role in the Scrum framework?
- A. Database Admin
- B. Development Team
- C. QA Tester
- D. Senior Developer
Answer: B
NEW QUESTION 4
During the sprint review the project is assessed against the _____
- A. Sprint goal
- B. Sprint Planning
- C. Sprint review
- D. Sprint retrospective
Answer: A
NEW QUESTION 5
The Product Backlog is maintained by:
- A. The Scrum Master
- B. The Development Team
- C. The Product Owner
- D. The Product Owner and Scrum Master
Answer: C
NEW QUESTION 6
Which of the following is not a Product Owner responsibility?
- A. Running the daily scrum meeting;
- B. Executando a reunião diária scrum ;
- C. Running the daily scrum meeting
- D. Gathering requirements for Product Backlog items
- E. Inspecting work at Sprint Review
Answer: A
NEW QUESTION 7
Which of the following is not a Product Owner responsibility?
- A. Maintaining the Product Backlog with current information
- B. Working with stakeholders to determine and detail product features
- C. Assigning tasks to team members
- D. Prioritizing the Product Backlog
Answer: C
NEW QUESTION 8
The ______ control model requires that every piece of work be completely understood.
- A. Defined process
- B. Empirical Process
- C. Incremental Process
- D. Six Sigm
- E. Process)
Answer: B
NEW QUESTION 9
What does the Sprint Backlog consist of?
- A. User Stories, only.
- B. Use Cases
- C. Selected Backlog Items and Tasks
- D. Test cases
Answer: C
NEW QUESTION 10
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
- A. The development team cannot meet their Sprint commitment to complete work if requirements are changing
- B. A Sprint cycle is not enough time for senior management review and approve changes
- C. This forces Product Owners to focus on what is really important for the team to develop.
- D. The development team must be able to limit the Product Owner authority
Answer: C
NEW QUESTION 11
What is the maximum amount of time that the team should spend in the daily scrum?
- A. As long as it takes
- B. 1 hour
- C. 45 minutes
- D. 15 minutes
- E. 15 minutes, proportionally less for shorter Sprints
Answer: D
NEW QUESTION 12
Which of the following are artifacts associated with Scrum?
- A. Product specification
- B. Effort chart
- C. Sprint backlog
- D. Product owner list
Answer: C
NEW QUESTION 13
What is the maximum amount of time a sprint retrospective should take?
- A. 1 hour
- B. 1 and half hour
- C. 3 hours, for an 30 days Sprint
Answer: C
NEW QUESTION 14
How many principles form the foundation of the Manifesto for Agile Software Development?
- A. 10
- B. 9
- C. 12
- D. 15
Answer: C
NEW QUESTION 15
True or False: The Scrum Framework encompasses rules or guidelines for architecture?
- A. True
- B. False
Answer: B
NEW QUESTION 16
Is Scrum Master a "management" position?
- A. Yes
- B. No
Answer: A
NEW QUESTION 17
The _____ Team is responsible for delivering potentially shippable product increments at the end of each Sprint.
- A. Development Team
- B. Scrum Team
- C. Cross-Functional Team
- D. Self-Managing Team
Answer: A
NEW QUESTION 18
What is an ideal size for a Scrum team?
- A. 13
- B. 4
- C. 7
- D. 10
Answer: C
NEW QUESTION 19
The correct sequence of events in using Scrum framework is as follows:
- A. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- B. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
- C. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- D. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective
Answer: B
NEW QUESTION 20
The Sprint Backlog is owned by?
- A. The Scrum Master
- B. The Product Owner
- C. The Development Team
- D. The Scrum Master and Development Team
Answer: C
NEW QUESTION 21
What is the maximum duration of each Sprint planning meeting section?
- A. 1 hour
- B. 30 minutes
- C. 4 hours
- D. 2 hours
- E. 15 minutes
Answer: C
NEW QUESTION 22
Which of the following is not a Scrum Master responsibility?
- A. Establish priorities together with product owner for Product Backlog items
- B. Preventing Senior Management from shifting team priorities
- C. Empowering the team
- D. Socializing scrum throughout the organization
Answer: B
NEW QUESTION 23
Which of the following is not a Scrum cycle activity?
- A. Sprint retrospective
- B. Daily scrum
- C. Weekly inspection
- D. Sprint planning
Answer: C
NEW QUESTION 24
......