Q11. - (Topic 1) 

In the planning phase of a project, which of the following activities is performed? 

A. Solicitation 

B. Perform a feasibility study 

C. Appoint a project team 

D. Project Charter 

Answer:


Q12. - (Topic 2) 

Which of the following allows the ability to assess the validity of a project during pivotal points within a schedule? 

A. Initial risk assessment 

B. Phase gates 

C. Milestone 

D. Project charter review 

Answer:


Q13. - (Topic 1) 

Please refer to the attached graphic and review the following task description. 

Which of the following is the project schedule critical path? 

A. A,E,F,B,G,H,D 

B. A,E,F,B,H,D 

C. A,G,H,D 

D. A,E,F,C,D 

Answer:


Q14. - (Topic 1) 

Which of the following areas is addressed in the Project Charter? 

A. Project team members 

B. Work Breakdown Structure (WBS) 

C. Business needs 

D. Communications venue 

Answer:


Q15. - (Topic 2) 

Which of the following are the steps required to validate a project charter? 

A. Business case, work breakdown structure, project justification, and stakeholder identification 

B. Business case, feasibility analysis, project justification, and stakeholder identification 

C. Business case, communication plan, project justification, and stakeholder identification 

D. Business case, project justification, feasibility analysis, and management plan 

Answer:


Renewal PK0-003 book:

Q16. - (Topic 3) 

Which of the following defines the purpose of a phase gate meeting? 

A. To evaluate project continuation 

B. To sign the project charter 

C. To close the project 

D. To discuss project communication 

Answer:


Q17. - (Topic 3) 

Halfway through a project, the customer lead retired and was replaced. The new lead attended a briefing on the project and let the project manager know the customer is dissatisfied with the performance of the project team. The new lead has called for the immediate termination of the project and has requested that all funds spent should be returned. Which of the following should the project manager do NEXT? 

A. Cancel the project but keep all funds that have already been allocated. 

B. Return funds as the customer is always right and should be happy. 

C. Schedule an executive meeting to determine how appropriate stakeholders want to continue. 

D. Inform the customer that funds cannot be returned due to the contractual agreement. 

Answer:


Q18. - (Topic 3) 

A quality management plan should contain which of the following pieces of information? 

A. Quality budget 

B. Quality personnel 

C. Quality metrics 

D. Quality certification 

Answer:


Q19. - (Topic 2) 

Given the following statement: 

Based on industry standards, the average cost for implementing new hardware to each site is $5000. 

In which of the following areas should this statement be located within a project scope document? 

A. Assumptions 

B. Technical specifications 

C. Constraints 

D. Cost-benefit analysis 

Answer:


Q20. - (Topic 2) 

Which of the following are parts of decision oversight? (Select TWO). 

A. Change control board 

B. Committee consulting 

C. Tollgate approval 

D. Audit trails 

E. Local laws 

Answer: A,B