Q131. - (Topic 1) 

A software project has just been completed. While measuring the success of the project, the project manager has found that the customer is dissatisfied with the functionality. Which of the following components has suffered in this project? 

A. Risk 

B. Quality 

C. Schedule 

D. Budget 

Answer:


Q132. - (Topic 2) 

The project manager of a large-scale project is conducting, participating in, and taking the minutes of the weekly team meeting. At the end of each meeting, the project manager realizes that there are agenda items that were not addressed and have to be carried over to the next meeting. Which of the following should the project manager do differently? 

A. Reduce the agenda items 

B. Increase the number of meetings 

C. Identify a scribe and facilitator 

D. Review the meeting expectations 

Answer:


Q133. - (Topic 3) 

A project resource identifies a critical requirement which was not in scope for the project. Adhering to which of the following documents will inform the resource of what to do FIRST? 

A. Change management form 

B. Communication plan 

C. Risk register 

D. WBS 

Answer:


Q134. - (Topic 1) 

Which of the following project plan components would include information regarding the management of issues? 

A. Project Management Plan 

B. Human Resources Plan 

C. Test Mangement Plan 

D. Scope Management Plan 

Answer:


Q135. - (Topic 1) 

The project has expended approximately 75% of the schedule, but has completed only 50% of the work. The customer has informed the project manager that the scheduled end date of the project is critical and cost may not increase. Which of the following techniques BEST meets the customers needs? (Select TWO). 

A. Abandoning the critical path 

B. Working on concurrent tasks consecutively to decrease cost variance 

C. Decrease the number of tasks 

D. Working on consecutive tasks concurrently to improve schedule variance 

E. Reduce the project’s scope 

Answer: D,E 


Up to the minute PK0-003 exam question:

Q136. - (Topic 1) 

Which of the following shows how often contracts would be closed for the procurements on a project? 

A. During phase gate review 

B. After the project is completed 

C. At the end of the project 

D. At the end of the contract 

Answer:


Q137. - (Topic 2) 

While creating a project schedule, multiple inputs were considered during estimating, allowing for the identification of best case, worst case, and expected case. Which of the following types of schedule methods will reflect this? 

A. PERT 

B. CPM 

C. CCM 

D. GERT 

Answer:


Q138. - (Topic 1) 

A project team is about to deliver on a two year long project when they are informed of new Government laws that directly affect the product. The team meets with their stakeholders to discuss the impact to the project and determine that additional laws need to be taken into account before go-live. The NEXT step the project manager needs to take is: 

A. re-direct the development team. 

B. create a change request. 

C. update the issues log. 

D. hold a meeting with the users. 

Answer:


Q139. - (Topic 2) 

A project activity has a schedule that allows a late start on day 10 and a late finish on day 

20. The project manager has determined an early start could occur on day 7 with an early finish on day 14. Which of the following does this schedule identify? 

A. A lead 

B. A buffer 

C. A float 

D. A lag 

Answer:


Q140. - (Topic 3) 

Approval from which of the following entities is required to make a project charter valid? 

A. Accounting 

B. Project sponsor 

C. Developer 

D. Legal 

Answer: