NEW QUESTION 1
Which of the following are inputs to Activity Definition?

  • A. Project Scope Statement and Work Breakdown Structure
  • B. Activity list and Arrow Diagram
  • C. Change Requests Lists and Organizational Process Assets
  • D. Project Management Plan and Resource Availability

Answer: A

NEW QUESTION 2
A required input for Create WBS is a project:

  • A. quality plan.
  • B. schedule network.
  • C. management document update.
  • D. scope statement.

Answer: D

NEW QUESTION 3
The procurement process that documents agreements and related documentation for future reference is known as:

  • A. Plan Procurements.
  • B. Control Procurements.
  • C. Close Procurements.
  • D. Conduct Procurements.

Answer: C

NEW QUESTION 4
What’s budget?

  • A. Monitoring & Controlling
  • B. Executing
  • C. Planning
  • D. Initiating

Answer: C

NEW QUESTION 5
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

  • A. One
  • B. Five
  • C. Six
  • D. Seven

Answer: C

NEW QUESTION 6
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

  • A. Negative
  • B. Zero
  • C. Positive
  • D. Free

Answer: C

NEW QUESTION 7
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

  • A. Critical path method
  • B. Variance analysis
  • C. Schedule compression
  • D. Schedule comparison bar charts

Answer: A

NEW QUESTION 8
An input to the Control Quality process is:

  • A. Activity attributes
  • B. Quality control measurements
  • C. Enterprise environmental factors
  • D. Deliverables

Answer: D

NEW QUESTION 9
Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?

  • A. Earned value performance
  • B. Trend analysis
  • C. Cost-benefit analysis
  • D. Variance analysis

Answer: B

NEW QUESTION 10
An imposed date for completion of the project by the customer is an example of a project:

  • A. deliverable
  • B. assumption
  • C. constraint
  • D. exclusion

Answer: C

NEW QUESTION 11
A key benefit of the Manage Communications process is that it enables:

  • A. The best use of communication methods.
  • B. An efficient and effective communication flow.
  • C. Project costs to be reduced.
  • D. The best use of communication technology.

Answer: B

NEW QUESTION 12
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

  • A. Mandatory
  • B. Discretionary
  • C. Internal
  • D. External

Answer: A

NEW QUESTION 13
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

  • A. Estimate Costs
  • B. Estimate Activity Resources
  • C. Control Costs
  • D. Determine Budget

Answer: B

NEW QUESTION 14
Which of the following is a schedule network analysis technique that takes limited resources into account?

  • A. Network reserve analysis
  • B. Critical chain method
  • C. Lead and lag adjustment
  • D. Critical path method

Answer: B

NEW QUESTION 15
What is the term assigned to products or services having the same functional use but different technical characteristics?

  • A. Scope
  • B. Quality
  • C. Specification
  • D. Grade

Answer: D

NEW QUESTION 16
In which Project Management Process Group is the project charter developed?

  • A. Monitoring and Controlling
  • B. Executing
  • C. Initiating
  • D. Planning

Answer: C

NEW QUESTION 17
Which of the following is an output of the Perform Integrated Change Control process?

  • A. Project document updates
  • B. Organizational process assets updates
  • C. Change requests
  • D. Deliverables

Answer: A

NEW QUESTION 18
Progressively elaborating high-level information into detailed plans is performed by the:

  • A. project management office
  • B. portfolio manager
  • C. program manager
  • D. project manager

Answer: D