Want to know features? Want to lear more about experience? Study . Gat a success with an absolute guarantee to pass PMP PMP (Project Management Professional) test on your first attempt.
Free PMP Demo Online For Microsoft Certifitcation:
NEW QUESTION 1
Which of the following are inputs to Activity Definition?
- A. Project Scope Statement and Work Breakdown Structure
- B. Activity list and Arrow Diagram
- C. Change Requests Lists and Organizational Process Assets
- D. Project Management Plan and Resource Availability
Answer: A
NEW QUESTION 2
A required input for Create WBS is a project:
- A. quality plan.
- B. schedule network.
- C. management document update.
- D. scope statement.
Answer: D
NEW QUESTION 3
The procurement process that documents agreements and related documentation for future reference is known as:
- A. Plan Procurements.
- B. Control Procurements.
- C. Close Procurements.
- D. Conduct Procurements.
Answer: C
NEW QUESTION 4
What’s budget?
- A. Monitoring & Controlling
- B. Executing
- C. Planning
- D. Initiating
Answer: C
NEW QUESTION 5
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
- A. One
- B. Five
- C. Six
- D. Seven
Answer: C
NEW QUESTION 6
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
- A. Negative
- B. Zero
- C. Positive
- D. Free
Answer: C
NEW QUESTION 7
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
- A. Critical path method
- B. Variance analysis
- C. Schedule compression
- D. Schedule comparison bar charts
Answer: A
NEW QUESTION 8
An input to the Control Quality process is:
- A. Activity attributes
- B. Quality control measurements
- C. Enterprise environmental factors
- D. Deliverables
Answer: D
NEW QUESTION 9
Which of the following methods of performance review examines project performance over time to determine if performance is improving or deteriorating?
- A. Earned value performance
- B. Trend analysis
- C. Cost-benefit analysis
- D. Variance analysis
Answer: B
NEW QUESTION 10
An imposed date for completion of the project by the customer is an example of a project:
- A. deliverable
- B. assumption
- C. constraint
- D. exclusion
Answer: C
NEW QUESTION 11
A key benefit of the Manage Communications process is that it enables:
- A. The best use of communication methods.
- B. An efficient and effective communication flow.
- C. Project costs to be reduced.
- D. The best use of communication technology.
Answer: B
NEW QUESTION 12
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
- A. Mandatory
- B. Discretionary
- C. Internal
- D. External
Answer: A
NEW QUESTION 13
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
- A. Estimate Costs
- B. Estimate Activity Resources
- C. Control Costs
- D. Determine Budget
Answer: B
NEW QUESTION 14
Which of the following is a schedule network analysis technique that takes limited resources into account?
- A. Network reserve analysis
- B. Critical chain method
- C. Lead and lag adjustment
- D. Critical path method
Answer: B
NEW QUESTION 15
What is the term assigned to products or services having the same functional use but different technical characteristics?
- A. Scope
- B. Quality
- C. Specification
- D. Grade
Answer: D
NEW QUESTION 16
In which Project Management Process Group is the project charter developed?
- A. Monitoring and Controlling
- B. Executing
- C. Initiating
- D. Planning
Answer: C
NEW QUESTION 17
Which of the following is an output of the Perform Integrated Change Control process?
- A. Project document updates
- B. Organizational process assets updates
- C. Change requests
- D. Deliverables
Answer: A
NEW QUESTION 18
Progressively elaborating high-level information into detailed plans is performed by the:
- A. project management office
- B. portfolio manager
- C. program manager
- D. project manager
Answer: D
P.S. Easily pass PMP Exam with 918 Q&As Surepassexam Dumps & pdf Version, Welcome to Download the Newest Surepassexam PMP Dumps: https://www.surepassexam.com/PMP-exam-dumps.html (918 New Questions)