We offers . "Managing Projects and Portfolios with Microsoft PPM (beta)", also known as 70-348 exam, is a Microsoft Certification. This set of posts, Passing the 70-348 exam with , will help you answer those questions. The covers all the knowledge points of the real exam. 100% real and revised by experts!

Also have 70-348 free dumps questions for you:

NEW QUESTION 1
DRAG DROP
You are project manager in your company’s PMO. You have permission to manage the Enterprise Global view in Microsoft PPM. Your organization works with many large multiyear projects often managed by more than one project manager.
You need to provide an Enterprise Global view that displays the fields necessary for your colleagues to control whether a task is published, who will be responsible for sending the task updates for the task, and who is responsible for approving updates from resources.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
70-348 dumps exhibit

    Answer:

    Explanation: 70-348 dumps exhibit

    NEW QUESTION 2
    Your company has had several large projects fail due to cost overruns and the lack of available resources. These projects use an enterprise project type named Large IT Project and use a workflow to govern the approval of the projects. The workflow consists of four phases: Initiate, Plan, Execute, and Close.
    You need to use Microsoft PPM to compare the value that a new project provides with the cost of implementing the project.
    Which three configuration changes should you make? Each correct answer presents part of the solution.

    • A. Navigate to PWA Setting
    • B. Edit the Large IT Project project type, and in the Available Project Detail Page section, add the Strategic Impact form.
    • C. Create a project-level custom field that will be used to enter the total cost of a project.
    • D. Define your company’s strategic drivers, and enter them into the Strategic Impact form.
    • E. Create a project-level custom field that will be used to enter the value statements of why this project should be undertaken.
    • F. Define your company’s strategic drivers and enter them into the driver library.
    • G. In PWA Settings, edit and then save the stage informatio
    • H. In the Available Project Detail Page section, add the Strategic Impact form.

    Answer: ABE

    NEW QUESTION 3
    You use Microsoft PPM to manage an e-commerce portal development program.
    The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level.
    You need to be able to see all programs and their associated individual projects from within Project Center.
    What should you do?

    • A. Select the Enterprise Project Type Name field as the value for grouping.
    • B. Select the Master Program field as the value for filtering.
    • C. Select the Subprojects check box.
    • D. Select the Project Details view.

    Answer: C

    NEW QUESTION 4
    DRAG DROP
    You are the Microsoft PPM administrator for a large organization.
    You need to ensure that line managers can delegate timesheet approvals to their team members.
    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
    70-348 dumps exhibit

      Answer:

      Explanation: References:
      https://technet.microsoft.com/en-us/library/cc197631.aspx

      NEW QUESTION 5
      HOTSPOT
      You use Microsoft PPM to manage projects. You plan to use milestones in a project.
      For each of the following statements, select Yes if the statement is true. Otherwise, select No.
      70-348 dumps exhibit

        Answer:

        Explanation: 70-348 dumps exhibit

        NEW QUESTION 6
        You are the administrator for an organization that uses Microsoft PPM. The IT department has 10 developers. You assign all developers to a team named Developers. The IT manager plans to use the team feature of Microsoft PPM.
        You need to ensure that all project managers can use Team assign instead of Resource assign.
        What should you do to finish the Developers team configuration?

        • A. Create a generic resource named Developers that is not assigned to the Developers tea
        • B. Select the Team Assignment Pool option for the resource.
        • C. Create a generic resource named Developers.
        • D. Create a generic resource named Developer
        • E. Assign the resource to the Developers team.
        • F. Create a generic resource named Developers that is assigned to the Developers tea
        • G. Select the Team Assignment Pool option for the resource.

        Answer: D

        Explanation: References:
        http://www.mpug.com/articles/working-teams-project-onlineproject-server-2013/

        NEW QUESTION 7
        The SharePoint Farm administrator for a company installs Microsoft PPM and grants you administrative rights for PWA. The PWA instance is accessible at the URL: https://AppServer/Live.
        You determine that the client needs to implement a Resource Breakdown Structure (RBS) to provide access to projects.
        You need to ensure that the RBS is implemented. What should you do first?

        • A. Run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
        • B. Ask the SharePoint administrator to run the Set-SPProjectPermissionMode Windows PowerShell cmdlet.
        • C. From Settings, select Manage Groups.
        • D. From Site Settings, activate the Project Web App Connectivity feature.

        Answer: B

        NEW QUESTION 8
        HOTSPOT
        You create a new project plan. You plan to take a snapshot of the project before and after the project start date.
        For each of the following statements, select Yes if the statement is true. Otherwise, select
        No.
        70-348 dumps exhibit

          Answer:

          Explanation: The first baseline happens after the planning stage of the project. It is a snapshot of the planned timescales.
          At the start of a project, when the manager has all the tasks in place, the people are assigned and the money is budgeted, he creates a baseline of data for his project so that he can measure its progress.
          References:
          https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-7E775482-AC84-4F4A-BBD0-592F9AC91953

          NEW QUESTION 9
          HOTSPOT
          Your organization uses Microsoft PPM for tracking projects.
          For one specific cross-functional project, different managers are responsible for different phases. These managers must be able to receive the task status updates for the project tasks that they are responsible for.
          For each of the following statements, select Yes if the statement is true. Otherwise, select No.
          70-348 dumps exhibit

            Answer:

            Explanation: References:
            https://support.office.com/en-gb/article/Status-Manager-task-field-4bc59e8b-fa20-415f-acd0-393b8572e6c4

            NEW QUESTION 10
            You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost, Proposed Benefits, and Sponsor Name properties.
            The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
            You need to use a project approval workflow.
            Which three objects should use? Each correct answer presents part of the solution.

            • A. Project Departments
            • B. Enterprise Project types
            • C. Project Detail Pages
            • D. Project schedule templates
            • E. Phases and stages

            Answer: BCE

            NEW QUESTION 11
            DRAG DROP
            You are an administrator for your company’s Microsoft PPM environment. You implement several project level enterprise custom fields and add these fields to new and existing views.
            Some users report they spend too much time scrolling left and right in a view named Team Status. You determine that the column width for the Enterprise Project Type field may be causing the issue.
            You need to reduce the amount of scrolling.
            Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
            70-348 dumps exhibit

              Answer:

              Explanation: 70-348 dumps exhibit

              NEW QUESTION 12
              DRAG DROP
              You are a project manager in an organization that is using Microsoft PPM for work management.
              You have already accepted all status updates in the Approval Center, but you are still unable to see the updates in your project schedule.
              You need to ensure that status updates are reflected in your project schedule.
              Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
              70-348 dumps exhibit

                Answer:

                Explanation: 70-348 dumps exhibit

                NEW QUESTION 13
                DRAG DROP
                You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
                You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
                Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
                70-348 dumps exhibit

                  Answer:

                  Explanation: References:
                  https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-7E775482-AC84-4F4A-BBD0-592F9AC91953

                  NEW QUESTION 14
                  You are project manager for an organization that is uses Microsoft PPM. You need to create a project deliverable for the current project.
                  What should you do?

                  • A. In Microsoft Project, manage a deliverable.
                  • B. On the project site, edit the list to include the Task ID attribute.
                  • C. In Microsoft Project, use Sync Deliverables.
                  • D. On the project site, create a new item in the Deliverables list.

                  Answer: D

                  Explanation: References:
                  https://diegocampereira.com/2021/02/10/creating-deliverables-using-microsoft-project-professional-and-project-site/

                  NEW QUESTION 15
                  This question requires that you evaluate the underlined text to determine if it is correct.
                  To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.
                  Review the underlined text. If it makes the statement correct, select “No change is needed.” If the statement is incorrect, select the answer choice that makes the statement correct.

                  • A. No change is needed.
                  • B. Capacity Planning page.
                  • C. Resource Plan view in Microsoft Project
                  • D. Manage Users page

                  Answer: A

                  Explanation: References:
                  http://www.mpug.com/articles/understanding-resource-engagements-in-microsoft-project- 2021/

                  NEW QUESTION 16
                  You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development.
                  You have the following requirements:
                  You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM.
                  Where should you add resources?

                  • A. in the e-commerce portal development program project site
                  • B. in the individual project schedules
                  • C. in Build Team, in the e-commerce portal development program schedule
                  • D. in the individual project sites

                  Answer: C

                  NEW QUESTION 17
                  HOTSPOT
                  You are a project manager and want to display key deliverables associated with your project. The tasks that produce the deliverables are already on the project schedule.
                  You need to ensure that the deliverables are visible on the project site.
                  For each of the following statements, select Yes if the statement is true. Otherwise, select No.
                  70-348 dumps exhibit

                    Answer:

                    Explanation: References:
                    https://diegocampereira.com/2021/02/10/creating-deliverables-using-microsoft-project-professional-and-project-site/