Ucertify PRINCE2-Foundation Questions are updated and all PRINCE2-Foundation answers are verified by experts. Once you have completely prepared with our PRINCE2-Foundation exam prep kits you will be ready for the real PRINCE2-Foundation exam without a problem. We have Most recent PRINCE2-Exams PRINCE2-Foundation dumps study guide. PASSED PRINCE2-Foundation First attempt! Here What I Did.
Online PRINCE2-Exams PRINCE2-Foundation free dumps demo Below:
NEW QUESTION 1
When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
- A. A substantial amount of the project budget is to be spent
- B. More human resources are required than in other stages
- C. The risk is lower
- D. No changes to the project management team are envisaged
Answer: C
NEW QUESTION 2
Which is NOT a purpose of a Benefits Review Plan?
- A. Define the periodover which the cost-benefit analysis will be based
- B. Describe how to measure the performance of the project's products in operational use
- C. Define the scope, timing and ownership of the benefit reviews required
- D. Describe how to measure and confirm anybenefits that are to be realised after the project is closed
Answer: A
NEW QUESTION 3
Which is a purpose of the Business Case theme?
- A. Identify which role is responsible for producing the Business Case
- B. Identify the project'soutputs
- C. Establish the controls to manage changes that may impact the project benefits
- D. Establish a viable investment proposition
Answer: D
NEW QUESTION 4
Which role is responsible for creating Checkpoint Reports?
- A. Senior Supplier
- B. Team Manager
- C. Change Authority
- D. Project Support
Answer: B
NEW QUESTION 5
Which is NOT a PRINCE2 principle?
- A. Learn from experience
- B. Customer/supplier environment
- C. Defined roles and responsibilities
- D. Continued business justification
Answer: B
NEW QUESTION 6
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
- A. Those with a financial interest in the project
- B. Those who will manage the project on a day-to-day basis
- C. Those who will specify the desired outputs of the project
- D. Those who will create the project's outputs
Answer: B
NEW QUESTION 7
Which is NOT one of the levels of plan recommended by PRINCE2?
- A. Benefits Review Plan
- B. Project Plan
- C. Stage Plan
- D. Team Plan
Answer: A
NEW QUESTION 8
Which describes a risk event?
- A. The area of uncertainty in terms of the threat or opportunity
- B. Thederivation or sources of a potential risk to the project
- C. The achievement of a milestone on the Project Plan
- D. The sequence of events and actions that will be put in place if a risk occurs
Answer: A
NEW QUESTION 9
Which characteristic distinguishes a project from regular business operations?
- A. Produces benefits
- B. Introduces business change
- C. Manages stakeholders
- D. Incurs cost
Answer: B
NEW QUESTION 10
In which product would you find a product's quality tolerance defined?
- A. Product Description
- B. Quality Management Strategy
- C. Quality Register
- D. Configuration Item Record
Answer: A
NEW QUESTION 11
Which is NOT one of the PRINCE2 integrated elements?
- A. Tailoring PRINCE2 to the project environment
- B. The processes
- C. The products
- D. The themes
Answer: C
NEW QUESTION 12
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ?] the project's plans
- A. define a coding system to provide a unique identifier for the products within
- B. summarize the results of the quality activities performed on
- C. provide a framework to design, develop and maintain
- D. define the project benefits to be achieved by each of
Answer: C
NEW QUESTION 13
Which is a purpose of the Managing Product Delivery process?
- A. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
- B. Provide a controlled link between the Project Manager and the Team Manager(s)
- C. Enable the Project Board to requestupdates to the current Team Plan
- D. Establish solid foundations for the project
Answer: B
NEW QUESTION 14
Which two roles are linked by the Managing Product Delivery process?
- A. Corporate or programme management and Project Board
- B. Project Board and Project Manager
- C. Project Manager and TeamManager
- D. Team Manager and external supplier
Answer: C
NEW QUESTION 15
Identify the missing word in the following sentence, A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.
- A. Change
- B. Plans
- C. Progress
- D. Risk
Answer: C
NEW QUESTION 16
When are tolerances for a Work Package agreed?
- A. When acceptinga Work Package
- B. As work on each product within the Work Package begins
- C. Once ail products have been developed and approved
- D. When the Stage Plan is authorized by the Project Board
Answer: A
NEW QUESTION 17
Who should act as the communication channel between a project and corporate or programme management?
- A. Project Board
- B. Project Assurance
- C. Project Manager
- D. Project Support
Answer: A
NEW QUESTION 18
Which is a type of issue?
- A. A lesson
- B. A request for change
- C. An Exception Report
- D. A risk with an estimated high impact
Answer: B
NEW QUESTION 19
Which should be provided by corporate or programme management before the Starting up a Project process commences?
- A. A Project Brief
- B. Sufficient information to identify the prospective Executive
- C. The Project Initiation Documentation
- D. Authority to initiate a project
Answer: B
NEW QUESTION 20
Which is a task of product-based planning?
- A. Design the plan
- B. Create the product flow diagram
- C. Analyze the risks
- D. Prepare the schedule
Answer: B
NEW QUESTION 21
What theme provides the justification for the project?
- A. Quality
- B. Plans
- C. Progress
- D. Business Case
Answer: D
NEW QUESTION 22
What process is used by the Project Board to respond to an Exception Report?
- A. Controlling a Stage
- B. Managing a Stage Boundary
- C. Managing Product Delivery
- D. Directing a Project
Answer: D
NEW QUESTION 23
Which is a true statement about PRINCE2 event-driven controls
- A. Event-driven controls take place at predefined periodicintervals
- B. Event-driven controls are produced at the frequency defined in a Work Package
- C. Event-driven controls are used for decision making
- D. Checkpoint Reports are event-driven controls
Answer: C
NEW QUESTION 24
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
- A. Project Manager
- B. Executive
- C. corporate or programme management organization
- D. Suppliergroups
Answer: C
NEW QUESTION 25
Which process provides the Project Board with the information it requires in order to commit
resources to the project?
- A. Managing Product Delivery
- B. Initiating a Project
- C. Controlling a Stage
- D. Directinga Project
Answer: B
NEW QUESTION 26
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
- A. Controlling a Stage
- B. Closing a Project
- C. Directing a Project
- D. Managing a Stage Boundary
Answer: D
NEW QUESTION 27
Which role is responsible for specifying the project benefits?
- A. Corporate or programmemanagement
- B. Executive
- C. Senior User(s)
- D. Project Manager
Answer: C
NEW QUESTION 28
Which is a benefit of using PRINCE2?
- A. Is a method specifically designed for technical projects
- B. Provides for the efficient and economic use of management time
- C. Includes many of the proven planning techniques, such as critical path analysis
- D. Can be used tomanage both projects and programmes
Answer: B
NEW QUESTION 29
......