NEW QUESTION 1
Which is a tool or technique used in Define Scope?
- A. Templates, forms, and standards
- B. Change requests
- C. Product analysis
- D. Project assumptions
Answer: C
NEW QUESTION 2
When does Monitor and Control Risks occur?
- A. At project initiation
- B. During work performance analysis
- C. Throughout the life of the project
- D. At project milestones
Answer: C
NEW QUESTION 3
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
- A. risk management plan
- B. human resource management plan
- C. scope management plan
- D. procurement management plan
Answer: D
NEW QUESTION 4
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
- A. Collect Requirements
- B. Direct and Manage Project Execution
- C. Monitor and Control Project Work
- D. Develop Project Management Plan
Answer: D
NEW QUESTION 5
Which is an enterprise environmental factor?
- A. Marketplace conditions
- B. Policies and procedures
- C. Project files from previous projects
- D. Lessons learned from previous projects
Answer: A
NEW QUESTION 6
The organizational process assets that are of particular importance to Plan Communications are:
- A. Formal plans and procedures
- B. Lessons learned and historical information
- C. Guidelines and knowledge bases
- D. Stakeholder positions and their influence
Answer: B
NEW QUESTION 7
Who is responsible for developing the project management plan and all related component plans?
- A. Project team
- B. Portfolio manager
- C. Project manager
- D. Project management office
Answer: C
NEW QUESTION 8
Information collected on the status of project activities being performed to accomplish the project work is known as what?
- A. Project management information system
- B. Work performance information
- C. Work breakdown structure
- D. Variance analysis
Answer: B
NEW QUESTION 9
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
- A. Control Scope
- B. Collect Requirements
- C. Create WBS
- D. Define Scope
Answer: B
NEW QUESTION 10
The project manager needs to review the templates in use. The templates are part of the:
- A. Enterprise environmental factors.
- B. Historical information,
- C. Organizational process assets.
- D. Corporate knowledge base.
Answer: C
NEW QUESTION 11
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
- A. Mitigate
- B. Transfer
- C. Share
- D. Avoid
Answer: C
NEW QUESTION 12
The following is a network diagram for a project.
The free float for Activity H is how many days?
- A. 4
- B. 5
- C. 10
- D. 11
Answer: A
NEW QUESTION 13
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
- A. Portfolio
- B. Process
- C. Project
- D. Program
Answer: B
NEW QUESTION 14
Which characteristic do projects and operational work share in common?
- A. Performed by systems
- B. Constrained by limited resources
- C. Repetitiveness
- D. Uniqueness
Answer: B
NEW QUESTION 15
Another name for an Ishikawa diagram is:
- A. cause and effect diagram.
- B. control chart.
- C. flowchart.
- D. histogram.
Answer: A
NEW QUESTION 16
At the start of a typical project life cycle, costs are:
- A. low, peak as work is carried out, and drop as the project nears the end.
- B. low, become steady as work is carried out, and increase as the project nears the end.
- C. high, drop as work is carried out, and increase as the project nears the end.
- D. high, become low as work is carried out, and drop as the project nears the end.
Answer: A
NEW QUESTION 17
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
- A. Critical path method
- B. Critical chain method
- C. Resource leveling
- D. Schedule network analysis
Answer: B
NEW QUESTION 18
Which items are an output of the Perform Integrated Change Control process?
- A. Work performance reports
- B. Accepted deliverables
- C. Project management plan updates
- D. Organizational process assets
Answer: C