NEW QUESTION 1
Which is a tool or technique used in Define Scope?

  • A. Templates, forms, and standards
  • B. Change requests
  • C. Product analysis
  • D. Project assumptions

Answer: C

NEW QUESTION 2
When does Monitor and Control Risks occur?

  • A. At project initiation
  • B. During work performance analysis
  • C. Throughout the life of the project
  • D. At project milestones

Answer: C

NEW QUESTION 3
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

  • A. risk management plan
  • B. human resource management plan
  • C. scope management plan
  • D. procurement management plan

Answer: D

NEW QUESTION 4
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

  • A. Collect Requirements
  • B. Direct and Manage Project Execution
  • C. Monitor and Control Project Work
  • D. Develop Project Management Plan

Answer: D

NEW QUESTION 5
Which is an enterprise environmental factor?

  • A. Marketplace conditions
  • B. Policies and procedures
  • C. Project files from previous projects
  • D. Lessons learned from previous projects

Answer: A

NEW QUESTION 6
The organizational process assets that are of particular importance to Plan Communications are:

  • A. Formal plans and procedures
  • B. Lessons learned and historical information
  • C. Guidelines and knowledge bases
  • D. Stakeholder positions and their influence

Answer: B

NEW QUESTION 7
Who is responsible for developing the project management plan and all related component plans?

  • A. Project team
  • B. Portfolio manager
  • C. Project manager
  • D. Project management office

Answer: C

NEW QUESTION 8
Information collected on the status of project activities being performed to accomplish the project work is known as what?

  • A. Project management information system
  • B. Work performance information
  • C. Work breakdown structure
  • D. Variance analysis

Answer: B

NEW QUESTION 9
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

  • A. Control Scope
  • B. Collect Requirements
  • C. Create WBS
  • D. Define Scope

Answer: B

NEW QUESTION 10
The project manager needs to review the templates in use. The templates are part of the:

  • A. Enterprise environmental factors.
  • B. Historical information,
  • C. Organizational process assets.
  • D. Corporate knowledge base.

Answer: C

NEW QUESTION 11
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

  • A. Mitigate
  • B. Transfer
  • C. Share
  • D. Avoid

Answer: C

NEW QUESTION 12
The following is a network diagram for a project.
PMP dumps exhibit
The free float for Activity H is how many days?

  • A. 4
  • B. 5
  • C. 10
  • D. 11

Answer: A

NEW QUESTION 13
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

  • A. Portfolio
  • B. Process
  • C. Project
  • D. Program

Answer: B

NEW QUESTION 14
Which characteristic do projects and operational work share in common?

  • A. Performed by systems
  • B. Constrained by limited resources
  • C. Repetitiveness
  • D. Uniqueness

Answer: B

NEW QUESTION 15
Another name for an Ishikawa diagram is:

  • A. cause and effect diagram.
  • B. control chart.
  • C. flowchart.
  • D. histogram.

Answer: A

NEW QUESTION 16
At the start of a typical project life cycle, costs are:

  • A. low, peak as work is carried out, and drop as the project nears the end.
  • B. low, become steady as work is carried out, and increase as the project nears the end.
  • C. high, drop as work is carried out, and increase as the project nears the end.
  • D. high, become low as work is carried out, and drop as the project nears the end.

Answer: A

NEW QUESTION 17
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

  • A. Critical path method
  • B. Critical chain method
  • C. Resource leveling
  • D. Schedule network analysis

Answer: B

NEW QUESTION 18
Which items are an output of the Perform Integrated Change Control process?

  • A. Work performance reports
  • B. Accepted deliverables
  • C. Project management plan updates
  • D. Organizational process assets

Answer: C