Cause all that matters here is passing the CompTIA PK0-004 exam. Cause all that you need is a high score of PK0-004 CompTIA Project+ Certification Exam exam. The only one thing you need to do is downloading Actualtests PK0-004 exam study guides now. We will not let you down with our money-back guarantee.


♥♥ 2021 NEW RECOMMEND ♥♥

Free VCE & PDF File for CompTIA PK0-004 Real Exam (Full Version!)

★ Pass on Your First TRY ★ 100% Money Back Guarantee ★ Realistic Practice Exam Questions

Free Instant Download NEW PK0-004 Exam Dumps (PDF & VCE):
Available on: http://www.surepassexam.com/PK0-004-exam-dumps.html

Q11. Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:

A. follow the change process flow and notify the legal department after the change is implemented.

B. extend a formal invitation to the legal department representative to join the CCB.

C. hold a separate meeting with the legal department representative and ask for approval.

D. notify the legal department representative in the event of an upcoming audit.

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 294


Q12. A customer will have ongoing changes to project requirements.

Which of the following is the BEST project management methodology for this requirement?

A. Waterfall

B. Agile

C. PRINCE2

D. Bottom-up

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 310


Q13. Which of the following is a schedule that illustrates the duration of an activity?

A. Process diagram

B. Ishikawa diagram

C. Gantt chart

D. Pareto chart

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 168


Q14. A project requires daily status updates.

Which of the following is the MOST effective method for providing these updates?

A. Backlog

B. Standup

C. Kickoff

D. Retrospective

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 306


Q15. A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

A. Project schedule

B. Cost plan

C. Scope statement

D. Impact assessment

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,

Indianapolis, 2021, p. 156


Q16. A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

A. Project charter

B. Project management plan

C. Project statement of work

D. Project schedule

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 299


Q17. The project manager has noticed a vendor is not performing in accordance with the SLA.

Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?

A. Balanced score card

B. WBS

C. Post-project evaluation

D. PERT

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 332


Q18. A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.

The project manager is concerned that the requests will lead to:

A. quality control issues.

B. additional risks.

C. scope creep.

D. time constraints.

Answer: D


Q19. Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.

This type of conflict resolution is known as:

A. forcing.

B. avoiding.

C. smoothing.

D. compromising.

Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2021, p. 200


Q20. A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority.

Which of the following effects is this MOST likely to have on the project?

A. The deliverables and quality will remain the same, but the cost will increase.

B. The deliverables and quality will remain the same, but the cost will decrease.

C. The deliverables and cost will remain the same, but the quality will increase.

D. The cost and quality will remain the same, but the deliverables will increase.

Answer: A