NEW QUESTION 1

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

  • A. Plan Cost Management
  • B. Plan Scope Management
  • C. Plan Stakeholder Management
  • D. Plan Schedule Management

Answer: C

NEW QUESTION 2

Which of the following is a group decision-making technique?

  • A. Brainstorming
  • B. Focus groups
  • C. Affinity diagram
  • D. Plurality

Answer: D

NEW QUESTION 3

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

  • A. majority rule technique.
  • B. nominal group technique.
  • C. Delphi technique,
  • D. idea/mind mapping techniqu

Answer: B

NEW QUESTION 4

Change requests are processed for review and disposition according to which process?

  • A. Control Quality
  • B. Control Scope
  • C. Monitor and Control Project Work
  • D. Perform Integrated Change Control

Answer: D

NEW QUESTION 5

What is the function of a Project Management Office (PMO)?

  • A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.
  • B. To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.
  • C. To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.
  • D. To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work package

Answer: A

NEW QUESTION 6

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

  • A. Validate Scope.
  • B. Plan Scope Management.
  • C. Control Scope.
  • D. Define Scop

Answer: C

NEW QUESTION 7

Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?

  • A. Control Scope
  • B. Collect Requirements
  • C. Create WBS
  • D. Define Scope

Answer: B

NEW QUESTION 8

Which of the following statements correctly characterizes pull communication?

  • A. It includes letters, memos, reports, emails, and faxes.
  • B. It requires recipients to access communication content at their own discretion.
  • C. It is the most efficient way to ensure a common understanding among all participants.
  • D. It is primarily used when the volume of information to be transferred is minima

Answer: B

NEW QUESTION 9

Which of the following characteristics are found in a functional organizational structure?

  • A. Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget
  • B. Limited project manager authority, limited resource availability, and a part-time project manager's role
  • C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role
  • D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Answer: A

NEW QUESTION 10

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

  • A. Work breakdown structure
  • B. Organizational breakdown structure
  • C. Resource breakdown structure
  • D. Bill of materials

Answer: A

NEW QUESTION 11

In which domain of project management would a Pareto chart provide useful information?

  • A. Project Scope Management
  • B. Project Time Management
  • C. Project Communications Management
  • D. Project Quality Management

Answer: D

NEW QUESTION 12

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

  • A. Control Schedule
  • B. Define Activities
  • C. Develop Schedule
  • D. Estimate Activity Resources

Answer: D

NEW QUESTION 13

Which tool or technique is used to develop the human resource management plan?

  • A. Ground rules
  • B. Expert judgment
  • C. Team-building activities
  • D. Interpersonal skills

Answer: B

NEW QUESTION 14

A method to manage stakeholder expectations in the scope statement is to clearly:

  • A. state the guiding principles of the organization.
  • B. identify alternatives to generate different approaches.
  • C. state what is out of scope.
  • D. outline the results of the Delphi techniqu

Answer: C

NEW QUESTION 15

The individual or group that provides resources and support for a project and is accountable for success is the:

  • A. sponsor
  • B. customer
  • C. business partners
  • D. functional managers

Answer: A

NEW QUESTION 16

Typical outcomes of a project include:

  • A. Products, services, and improvements.
  • B. Products, programs, and services.
  • C. Improvements, portfolios, and services.
  • D. Improvements, processes, and product

Answer: A

NEW QUESTION 17

Administer Procurements is part of which Process Group?

  • A. Planning
  • B. Executing
  • C. Monitoring and Controlling
  • D. Closing

Answer: C

NEW QUESTION 18

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

  • A. Limited
  • B. Low to moderate
  • C. Moderate to high
  • D. High to almost total

Answer: C

NEW QUESTION 19

To which process is work performance information an input?

  • A. Administer Procurements
  • B. Direct and Manage Project Execution
  • C. Create WBS
  • D. Perform Qualitative Risk Analysis

Answer: A

NEW QUESTION 20

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

  • A. Cost variance (CV)
  • B. Cost performance index (CPI)
  • C. Budget at completion (BAC)
  • D. Variance at completion (VAC)

Answer: B

NEW QUESTION 21

Which of the following strategic considerations often results in project authorization?

  • A. Customer requests and/or issue resolution
  • B. Stakeholder expectations and/or strategic opportunity (business need)
  • C. Technological advancement and/or senior executive request
  • D. Market demand and/or legal requirements

Answer: D

NEW QUESTION 22

Which type of manager is assigned by the performing organization to lead the team that is responsible for achieving the project objectives?

  • A. Program
  • B. Functional
  • C. Project
  • D. Portfolio

Answer: C

NEW QUESTION 23

Which output is the approved version of the time-phased project budget?

  • A. Resource calendar
  • B. Scope baseline
  • C. Trend analysis
  • D. Cost baseline

Answer: D

NEW QUESTION 24

Success is measured by benefits realization for a:

  • A. strategic plan
  • B. project
  • C. portfolio
  • D. program

Answer: C

NEW QUESTION 25

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

  • A. Applying calendars
  • B. Resource leveling
  • C. Resource planning
  • D. Resource conflict management

Answer: B

NEW QUESTION 26

Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?

  • A. Collect Requirements
  • B. Direct and Manage Project Execution
  • C. Monitor and Control Project Work
  • D. Develop Project Management Plan

Answer: D

NEW QUESTION 27

The project scope statement and resource calendars are inputs to which Project Time Management process?

  • A. Sequence Activities
  • B. Estimate Activity Resources
  • C. Develop Schedule
  • D. Control Schedule

Answer: C

NEW QUESTION 28
......